This former coated fabrics factory site had been derelict for over 10 years, following multiple failed attempts at remediation.
Our client saw an opportunity to create a new community of 168 new homes, but first they needed to tackle:
A robust approach to soil and groundwater remediation would be required to gain regulatory approval and allow the project to go ahead.
We worked closely with the client consultant to establish solid remedial options, giving the regulator confidence that contamination reduction targets could be achieved. By engaging with the regulator early, we were able to discharge the planning conditions for the client.
Our team carried out the phased demolition of all six dilapidated buildings on the site. As part of this, we completed both Licensed and Notifiable Non-Licensed work to remove asbestos.
We broke out concrete hardstandings and removed underground structures using our own 3DMC plant to record turnover depths in real-time.
Excavated materials were compacted to an “end product” performance specification, with in-situ densities in excess of 95% of the maximum dry density to enable a Vibro-Stone Column foundation solution.
We carried out a 20-week programme of soil and groundwater treatment, using our own plant and UK-exclusive technologies.
Our team designed and built a bespoke groundwater treatment system, which extracted impacted groundwater from sumps across the site. An oil water separator was used to remove NAPL, followed by treatment of dissolved phase product via GAC vessels prior to foul sewer discharge under consent.
In-situ Chemical Oxidation, using Oxygen BioChem (OBC) from Carus, was used to treat residual impacted groundwater, while impacted soils were treated by bioremediation.
Site Area | 2.1ha |
Location | Salford |